All About MMCD MMCD Information MMCD Products, Services, & Customer Testimonials Master Municipal Construction Documents
 

 

 

 

 

 

         

 

 

 

 

 

 

 

SGC 4.12.4 –  Delete GC 4.12.4 and replace with the following

If the Contractor disagrees with the Contract Administrator’s determination of the Work not meeting the Specifications based on the results of inspection or testing required in the Contract Documents or ordered by the Contract Administrator, the Contractor may elect to carry out such further inspection or testing which the Contract Administrator agrees is acceptable for the purpose of determining whether the Work complies with the requirements of the Contract Documents

a)         If such further inspection or testing determines that the Work is not in accordance with the requirements of the Contract Documents, then the Contractor shall correct such Work and pay the costs of the inspection and testing including all costs of the correction and subsequent inspection and testing. 

 b)         If such further inspection or testing determines that the Work is in accordance with the requirements of the Contract Documents, then the Owner shall pay all costs of the inspection and testing. 

SGC 9.4.3  –  Delete GC 9.4.3 and replace with the following: 

A revised unit price shall be applicable and calculated as follows:

a)          in the case of a shortfall of more than the Variance Threshold Percentage:

  1. the revised unit price shall apply to all of the actual work performed for that item; and
     

  2. the revised unit price shall be determined so that the Contractor's total compensation for that item will be equal to the actual quantity multiplied by the tender unit price plus an amount equal to the overhead and profit, if any, the Contractor would have received for the quantity difference between the Tender Quantity as reduced by the Variance Threshold Percentage and the actual quantity; and

b)         in the case of an overrun of more than the Threshold  Variance Percentage of the Tender Quantity for that item: 

            i.         the original unit price shall apply to the Tender Quantity for that item plus the Threshold Variance Percentage and the revised unit price shall apply only to the quantity in excess of the Threshold Variance Percentage; and  

            ii.        a revised unit price, applicable to the quantity in excess of Tender Quantity plus the Threshold Variance Percentage for that item, shall be determined so that the Contractor receives an amount or revised unit prices as agreed by the parties, or failing agreement the actual costs of the excess plus markups as provided by GC 10.1. 

SGC 10.1.1 b) & c)  –  Delete GC 10.1.1 b) & c) and replace with the following

 b)         major equipment: 

            i)          Contractor Owned or Bare Rented - at the non-operated hourly rates as set out in the Approved Equipment Rental Rate Guide based on actual hours, in minimum increments of 0.5 hours, plus a 10% markup to cover all overhead costs and profit. If equipment is not listed in the Approved Equipment Rental Rate Guide then at a rate determined by the Contract Administrator based on local equipment rental rates; or 

            ii)         Non-Contractor Owned and Operated - at the lower of the all-found rate in the Approved Equipment Rental Rate Guide for operated equipment, or the actual rental costs incurred by the Contractor, as evidenced by invoice, plus, in either case, a 10% markup to cover all overhead costs and profit; 

            iii)         No separate rental for Small Tools

c)         materials incorporated into the Work or consumed in performing the Work by the Contractor shall be at the Contractor’s actual cost, as evidenced by invoice, including all transportation, freight and haulage costs plus a markup of 10% on such actual cost to cover all overhead, handling, and profit; 

SGC 13.8.1 a) –  Delete GC 13.8.1 a) and replace with the following 

a)         as a genuine pre-estimate of the Owner’s increased costs for the Contract Administrator and the Owner’s own staff caused by such delay an amount of $500.00 per day or pro rata portion for each Day that actual Substantial Performance is achieved after the Substantial Performance Milestone Date; plus 

SGC 18.3.1 –   Delete GC 18.3.1 and replace with the following 

            Except for items in the Schedule of Quantities and Prices which are identified as being "Supply Only" or items authorized under GC 10.1, payments shall not be made for materials or products purchased by the Contractor but not incorporated into the Work at the Place of the Work. 

SGC 18.4.1 –   Delete GC 18.4.1 and replace with the following 

            Builders Lien Holdback:  The Owner shall hold back 10%, or other percentage as required by the Builders Lien Act, of any amounts due to the Contractor as a builders lien holdback. 

SGC 21.2.1 –  Delete GC 21.2.1 and replace with the following 

            As part of the Work the Contractor shall, to the extent reasonably possible, perform on behalf of the Owner the obligations which the Owner must undertake as “Prime Contractor” by virtue of the Workers’ Compensation Act and Regulations, or other statutes.

SGC 24.1.1 b) –  Delete GC 24.1.1 b) and replace with the following 

b)         Comprehensive General Bodily Injury and Property Damage
Liability Insurance -

            Limits: Bodily Injury and Property Damage inclusive $5,000,000

The insurance shall include Contractor’s Contingent Liability, and Contractual Liability of sufficient scope to include the liability assumed by the Contractor under the terms of this Contract, and Completed Operations Liability. The policy shall include the Owner and the Contract Administrator as additional insureds with a cross liability clause. Any property damage deductible shall be for the account of the Contractor and shall not exceed $2,500.00 for any one occurrence.

 

The following Electrical Drawings have been revised:  [click here for PDF copies - in Zip file]

E1.6-Rev.1
Type C4 & C5 Spread Footing Concrete Bases

E1.11 - Rev.1
Types F1, L1 & S1 Spread Footing Shape Concrete Bases

E5.21 - Rev.1

Service Base

E7.3 - Rev.1
Pedestrian Pushbutton Post

E8.2 - Rev.1
Service Panel in Service Base (Mounting Details)

E8.3 - Rev.1
Service Panel in Service Base (Mounting Details)

E8.5 - Rev.1
60A (120/240V) Street Lighting Service Panel in Service Base (Wiring Diagram)

E8.6 - Rev.1
100A (120/240V) Traffic Signal/Street Lighting Service Panel in Service Base (Wiring Diagram)

E8.9 - Rev.1
100A (120/240V Traffic Signal/Street Lighting Service Panel (Wiring Diagram)

E8.10 - Rev.1
Service Ground Plate Installation Detail

E8.12 - Rev.1
Signal Cable Wiring in Pole Handhole

E8.13 - Rev.1
Signal Cable Colour Code Sample

E8.15 - Rev.1
Pole Mounted Receptacle

E9.4 - Rev.1
Detector Loop to Shielded Cable Splices